Neighborhood Updates

Following are the latest alerts on project activity for residential and business neighbors of the Downtown East project in terms of temporary construction traffic increases, temporary lane changes, unusual noise impact, or scheduled after-hours construction activity on site.

To receive notices via email, please click HERE to sign up for our neighborhood update mailing list.

10/22/2016: Crane assembly/disassembly and placing roof curbs. One lane of traffic on South 3rd Street will be closed during this work. 6:00 a.m. – 6:00 p.m.

10/03/2016: Pouring concrete decking. One lane of traffic on South 3rd Street will be closed during this work. 4:00 a.m. – 6:00 p.m.

09/16/2016: Pouring concrete decking for the mezzanine between 1st and 2nd Floor at the Millwright Building project. One lane of traffic on South 3rd Street will be closed during this work. 4:00 a.m. – 6:00 p.m.

09/14/2016: Pouring concrete decking for the 2nd Floor, West side, at the Millwright Building project. One lane of traffic on South 3rd Street will be closed during this work. 4:00 a.m. – 6:00 p.m.

09/12/2016: Pouring concrete decking for the 1st Floor, West side, at the Millwright Building project. One lane of traffic on South 3rd Street will be closed during this work. 4:00 a.m. – 6:00 p.m.

09/08/2016: Pouring concrete decking at the Millwright Building project. One lane of traffic on South 3rd Street will be closed during this work. 4:00 a.m. – 6:00 p.m.

09/06/2016: Pouring concrete decking at the Millwright Building project. One lane of traffic on South 3rd Street will be closed during this work. 4:00 a.m. – 6:00 p.m.

08/25-27/2016 and 08/29/2016: Pouring concrete decking at the Millwright Building project. One lane of traffic on South 3rd Street may be closed during this work. 4:00 a.m. – 6:00 p.m.

08/15/2016-8/19/2016: Pouring concrete decking at the Millwright Building project. One lane of traffic on South 3rd Street may be closed during this work. 4:00 a.m. – 6:00 p.m.

08/12/2016: Pouring concrete decking at the Millwright Building project. Two lanes of traffic on South 3rd Street may be closed during this work. 4:00 a.m. – 6:00 p.m.

08/08/2016: Pouring first floor concrete deck at the Millwright Building project. One lane of traffic on South 3rd Street to be closed. 4:00 a.m. – 4:00 p.m.

07/21/2016: Grand Opening of The Commons; East side of the park. 11:30 a.m. – 1:00 p.m.

07/20/2016: Grand Opening of the Wells Fargo Downtown East Campus; on Portland Avenue, between the Wells Fargo Towers. 1:00 p.m. – 2:00 p.m.

07/18/2016: Pouring of decorative concrete at the Downtown East Commons project. 6:00 a.m. – 5:00 p.m.

07/16/2016: Planting of shrubs and plants, soils importing, stone setting, and porous material paving at the Downtown East Commons project. 7:00 a.m. – 6:00 p.m.

07/11/2016: Pouring concrete paving in the morning and sawcutting concrete paving in the evening at the Downtown East Commons project. 6:00 a.m. – 9:00 p.m.

07/09/2016: Planting of shrubs and plants, soils importing, and stone setting. 7:00 a.m. – 6:00 p.m.

07/06/2016: Pouring concrete paving in the morning and sawcutting concrete paving in the evening at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 7:00 a.m. – 9:00 p.m.

07/05/2016: Pouring concrete paving in the morning and sawcutting concrete paving in the evening at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 6:00 a.m. – 9:00 p.m.

07/01/2016: Sawcutting concrete paving at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 4:00 a.m. through regular work hours that day.

06/25/2016: Moving heavy equipment and excavation at the Millwright Building project. 7:00 a.m. – 6:00 p.m.

06/18/2016: Planting trees, importing soils, and setting stones at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenues. Concrete pours, moving wall forms and earthwork at the Millwright Building project. 7:00 a.m. – 6:00 p.m.

06/15/2016: Sawcutting concrete paving at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 4:00 a.m. through regular work hours that day.

06/11/2016: Planting trees, importing soils, and setting stones at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 7:00 a.m. – 6:00 p.m.

06/10/2016: Pouring decorative concrete at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 6:00 a.m. through regular work hours that day.

06/9/2016: Sawcutting concrete paving at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 4:00 a.m. through regular work hours that day.

06/7/2016: Sawcutting concrete paving at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 4:00 a.m. through regular work hours that day.

06/4/2016: Planting trees, importing soils, and setting stones at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 8:00 a.m. – 6:00 p.m.

06/2/2016: Sawcutting concrete paving at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. 4:00 a.m. through regular work hours that day.

05/25/2016 & 5/26/2016: Sawcutting concrete paving at the Downtown East Commons project between South 4th and 5th Streets and Park and 5th Avenue. Starting at 4:00 a.m. Wednesday, May 25, 2016.

05/21/2016 & 5/22/2016: Utility work on 3rd Street South between 5th Avenue and Portland Avenue. 7:00 a.m. – 6:00 p.m.

05/21/2016: Grading, landscaping, and utility work at Downtown East Commons, between 4th and 5th Streets South and Park and 5th Avenue. 8:00 a.m. – 6:00 p.m.

05/17/2016: Concrete work on Downtown East Commons between 4th and 5th Streets South and Park and 5th Avenue. 5:00 a.m. – 8:00 p.m.

05/14/2016 & 05/15/2016: Installation of a new sewer line at the Radisson Red project on Park Avenue, South of 3rd Street. 6:00 a.m. – 6:00 p.m.

05/14/2016: Tree planting and moving of soils at Downtown East Commons between 4th and 5th Streets South and Park and 5th Avenue. 8:00 a.m. – 6:00 p.m.

05/13/2016: Concrete work on residential/retail space at 530 4th Street S. 7:00 a.m. – 10:00 p.m.

04/18/2016: Retention and earth work begins on Millwright Building.

04/11/2016 – 04/15/2016: Construction begins on the Millwright Building, 513 S 3rd Street. Construction fencing will be installed resulting in temporary closure of some adjacent sidewalks.